| Component | Description | Qty | Lead | Need date | PO release date | Preferred MFR | ITAR | M/B | Action |
|---|
| WO # | Build item | Qty | Start date | Need date | Routing | Status | MES |
|---|---|---|---|---|---|---|---|
| WO-2027-001-001 | STR-ASSY (Structure subsystem) | 1 | 2027-06-15 | 2027-09-01 | STR-RTG-001 (12 ops) | Planned | Pending MES selection |
| WO-2027-001-002 | EPS-ASSY (Power subsystem) | 1 | 2027-06-15 | 2027-09-01 | EPS-RTG-001 (8 ops) | Planned | Pending MES selection |
| WO-2027-001-003 | ADCS-ASSY | 1 | 2027-07-01 | 2027-09-15 | ADCS-RTG-001 (14 ops) | Planned | Pending MES selection |
| WO-2027-001-FINAL | SAT-001 (final integration) | 1 | 2027-10-01 | 2027-12-01 | SAT-RTG-FINAL (35 ops · 60 days) | Pending sub-assemblies | Pending MES selection |
| Component | Lead | PO start | In-house by | Schedule (May 2026 → Dec 2027) |
|---|
| Component | Arena Rev | NS Item Rev | Last sync | Status |
|---|---|---|---|---|
| SAT-001 | A | A | 2026-04-30 14:08 | In sync |
| COMM-RF-AMP-XBAND | B (per ECO-2026-0142) | B | 2026-04-30 14:08 | In sync |
| EPS-BATTERY-LIION-100W | A | A | 2026-04-30 14:08 | In sync |
| + 90 more rows · all in sync · daily reconciliation runs at 02:00 UTC · alerts on variance > 0 | ||||
The detailed BOM hierarchy lives in Arena PLM and is mirrored into NetSuite's Bill of Materials record. NS uses the BOM during MRP explosion to generate the planned POs above.
| Routing ID | Build item | Operations | Cycle time est | Linked WO | MES vendor |
|---|---|---|---|---|---|
| STR-RTG-001 | STR-ASSY (Structure) | 12 | 72 hrs | WO-2027-001-001 | TBD |
| EPS-RTG-001 | EPS-ASSY (Power) | 8 | 56 hrs | WO-2027-001-002 | TBD |
| ADCS-RTG-001 | ADCS-ASSY | 14 | 96 hrs | WO-2027-001-003 | TBD |
| SAT-RTG-FINAL | SAT-001 final integ | 35 | 480 hrs (60 days) | WO-2027-001-FINAL | TBD |
| Demand | Source | Qty | Need date | Supply | Supply source | Promise |
|---|---|---|---|---|---|---|
| SAT-001 | SO-2026-0341 line 4 | 1 | 2027-06-30 | WO-2027-001-FINAL | Make · MRP-released | 2027-06-15 |
| STR-ASSY | WO-2027-001-FINAL · op 010 | 1 | 2027-06-15 | WO-2027-001-001 | Sub-WO · Make | 2027-06-01 |
| ADCS-RW × 4 | WO-2027-001-003 · op 030 | 4 | 2026-06-15 | PO-2026-1148 | Buy · Blue Canyon | 2026-04-15 ✓ |
| EPS-PCDU | WO-2027-001-002 · op 020 | 1 | 2026-06-15 | PO-2025-2103 | Buy · AAC Clyde | 2026-03-15 ✓ |
| + 89 more pegging records · every demand line traces to its supply transaction | ||||||
| Demand source | Qty | Need date | Status | Pegged supply |
|---|---|---|---|---|
| SO-2026-0341 · CLIN-004 | 1 | 2027-06-30 | Active | WO-2027-001-FINAL |
| SAT-002 (option · pending SO) | 1 | 2028-06-30 | Forecast | Not yet planned |
| SAT-003 (forecast) | 1 | 2029-06-30 | Forecast | Not yet planned |
Project P&L roll-up lives in the Project Accounting + EVMS module. From here you can see the cost contribution of each MRP-released PO and WO into the project ledger.