| CLIN | Description | Method | BAC (cost) | PV YTD | EV YTD | AC YTD | CV | SV | CPI | SPI | % complete |
|---|---|---|---|---|---|---|---|---|---|---|---|
| CLIN-001 | PDR | Milestone | 6,400,000 | 6,400,000 | 6,400,000 | 6,180,000 | +220K | +0 | 1.04 | 1.00 | |
| CLIN-002 | CDR | Milestone | 9,750,000 | 9,750,000 | 9,750,000 | 9,420,000 | +330K | +0 | 1.04 | 1.00 | |
| CLIN-003 | Long-lead Procurement | Cost-to-cost | 17,200,000 | 6,880,000 | 6,020,000 | 5,790,000 | +230K | -860K | 1.04 | 0.87 | |
| CLIN-004 | Bus Manufacture | Units-of-prod | 45,500,000 | 2,420,000 | 2,650,000 | 2,580,000 | +70K | +230K | 1.03 | 1.10 | |
| CLIN-005 | AI&T | Cost-to-cost | 19,200,000 | 0 | 0 | 0 | 0 | 0 | — | — | |
| CLIN-006 | Launch Support | Milestone | 12,000,000 | 0 | 0 | 0 | 0 | 0 | — | — | |
| CLIN-007 | On-orbit Support | Stand-ready | 6,400,000 | 0 | 0 | 0 | 0 | 0 | — | — | |
| TOTALS | 116,200,000 | 19,450,000 | 18,820,000 | 17,970,000 | +850K | -630K | 1.04 | 0.97 | |||
| Risk # | Description | Subsystem | Probability | Impact | Exposure | Owner | Mitigation | Status |
|---|---|---|---|---|---|---|---|---|
| R-008 | PROP qual delay cascades to integration | PROP | 40% | $1.2M (penalty) | $480K | P. Reyes | Backup qual + expedite | Active · watching |
| R-014 | L3Harris payload qual finds rework | PAY | 25% | $1.6M | $400K | E. Garcia | TPI rep on-site weekly | Active |
| R-021 | TVAC chamber availability slips Stage 6 | AI&T | 30% | $680K (idle labour) | $204K | E. Garcia | Booked Wyle as backup | Active |
| R-027 | Launch slip from LV provider | Launch | 20% | $2.0M (storage + retest) | $400K | A. McLamb | 2 LV options under contract | Mitigated |
| R-031 | USML interpretation change · reclass | All | 15% | $3.5M (rework + delay) | $525K | Legal | State Dept advisory + DDTC monitor | Watching |
| Discipline | FTE planned | FTE actual | Hours YTD | Utilisation |
|---|---|---|---|---|
| Programme · PM/PE | 2.5 | 2.5 | 3,800 | 96% |
| Systems engineering | 4.0 | 3.8 | 5,920 | 92% |
| Mech / structures | 3.0 | 2.9 | 4,420 | 97% |
| EE / electronics | 4.5 | 4.6 | 7,180 | 102% |
| SW / FSW | 3.5 | 3.4 | 5,310 | 97% |
| Test / AI&T | 2.0 | 1.8 | 2,650 | 90% |
| Mfg techs (5 total) | 5.0 | 5.0 | 8,000 | 100% |
| QA | 1.5 | 1.5 | 2,310 | 100% |
| Total | 26.0 | 25.5 | 39,590 hrs | 98% |
| Milestone | Plan | Forecast | Variance | Status |
|---|---|---|---|---|
| PDR | 2025-04-30 | 2025-04-28 | +2d | ✓ Done |
| CDR | 2025-09-30 | 2025-09-29 | +1d | ✓ Done |
| LL Procure complete | 2026-08-31 | 2026-10-15 | -45d | ⚠ Slip · PROP |
| Bus integration done | 2026-08-15 | 2026-08-12 | +3d | ⚡ In progress |
| Functional test PASS | 2026-10-30 | 2026-10-30 | 0d | Planned |
| Environmental test PASS | 2027-03-15 | 2027-03-22 | -7d | Planned |
| Acceptance / DD-250 | 2027-09-15 | 2027-09-15 | 0d | Planned |
| Ship to launch site | 2027-10-15 | 2027-10-15 | 0d | Planned |
| LRD | 2027-12-01 | 2027-12-01 | 0d | Achievable |
Each CLIN has its own EV calculation based on the recognition method (milestone · cost-to-cost · units-of-production · stand-ready). The full table is shown above on the EVMS Dashboard tab. Click below for the corresponding revenue side.
Cost-loaded WBS that drives EV calculation. Full hierarchy shown on the EVMS Dashboard tab. WBS roll-up feeds CLIN earnings, project P&L, and CDRL A001.
Top 5 by exposure shown on the EVMS Dashboard tab. Quarterly export feeds CDRL A002.
Required for any > ±10% variance on the CDRL A001 monthly progress report. Full variance cards shown on the EVMS Dashboard tab.
| CDRL # | Description | Frequency | Source | Next due | Status |
|---|---|---|---|---|---|
| A001 | Monthly Progress Report (FFP) + EVMS | Monthly | Project EVMS · this page | 2026-05-31 | On track |
| A002 | Risk Register update | Quarterly | Project · risk register | 2026-06-30 | Q1 submitted |
| A003 | Subcontractor Status Report | Monthly | Procurement · vendor master | 2026-05-31 | On track |
| A004 | Test Plans / Procedures | Per phase | AI&T team | 2027-04-30 | Drafting |
| A005 | As-Built Configuration Drawings | End of CLIN-004 | Arena PLM export | 2027-06-30 | Pending build |
| Discipline | FTE planned | FTE actual | Hours YTD | Utilisation | Allocation |
|---|---|---|---|---|---|
| Programme · PM/PE | 2.5 | 2.5 | 3,800 | 96% | WBS 1.1 |
| Systems engineering | 4.0 | 3.8 | 5,920 | 92% | WBS 1.2 |
| Mech / structures | 3.0 | 2.9 | 4,420 | 97% | WBS 1.4 |
| EE / electronics | 4.5 | 4.6 | 7,180 | 102% | WBS 1.4 |
| SW / FSW | 3.5 | 3.4 | 5,310 | 97% | WBS 1.2 |
| Test / AI&T | 2.0 | 1.8 | 2,650 | 90% | WBS 1.5 |
| Mfg techs (5 total) | 5.0 | 5.0 | 8,000 | 100% | WBS 1.4 |
| QA | 1.5 | 1.5 | 2,310 | 100% | WBS 1.4 |
| Total | 26.0 | 25.5 | 39,590 hrs | 98% | — |